Post Falls I-90 Traffic Shift in October 2026: Seltice Way Detours

The Idaho Transportation Department plans to move both westbound lanes of I-90 over to the south side of the freeway around Oct. 20. They will run next to eastbound traffic for about a full year while crews rebuild the westbound lanes on the north side. Several of the closures that come with it, at the SH-41 on-ramp, under Huetter Road and along the Centennial Trail, send drivers, cyclists and walkers to Seltice Way. The City of Post Falls has spent this construction season rebuilding that same road.

So for the next year, the I-90 shift isn't something Post Falls drivers can simply route around. The corridor between Post Falls and Coeur d'Alene is a set of overlapping work zones, and the road holding the detours together is one of them.

October is a countdown

The crossover gets the headlines, but it comes at the end of a string of smaller closures that started Friday, Oct. 2. ITD has said the exact timing depends on how work goes in the weeks before the shift. As of today, Oct. 5, the schedule looks like this:

Date (2026) What changes Where drivers or trail users go
Oct. 2 to Oct. 9 Eastbound I-90 on-ramp from SH-41 closed 24/7 West on Seltice Way to the eastbound on-ramp near the Seltice Way bridge
Sept. 23 to Oct. 14 Centennial Trail closed for two miles, Pleasantview Road east toward Spokane Street Trail resurfacing by Kootenai County
Around Oct. 12 Westbound Northwest Boulevard on-ramp expected to reopen Reopening pushed back after crews found a problem where the ramp connects to I-90
Starting Oct. 12 Prairie Trail closed beneath I-90 for about a week Westbound bridge demolition begins
Oct. 16 to 18, tentative I-90 paving between US-95 and Northwest Boulevard One lane each direction, day and night
Around Oct. 20 Westbound I-90 crosses over to the south side Two lanes each way for about a year
After the shift Huetter Road closed beneath I-90 for up to two weeks Mullan Avenue or Poleline/Hanley north of I-90; Seltice Way south of it
Late October onward Overnight closures of the westbound SH-41 off-ramp for several weeks Timing to be announced

The SH-41 ramp closure, happening now, is a small preview of the next year. ITD sends eastbound drivers west on Seltice Way to the neighboring on-ramp, and the release asks drivers to plan for extra time and follow the posted detour signs. The westbound on-ramp and both SH-41 off-ramps stay open during that week.

What a year on the south side looks like

After the crossover, I-90 between SH-41 and US-95 keeps two lanes in each direction, separated by concrete barriers and with narrow shoulders. The westbound rest area closes to all traffic, including commercial vehicles. The eastbound rest area stays open.

Speed limits will change through the work zone. ITD uses variable speed limits on this project, with digital signs that adjust to nearby work, and it asks drivers to watch the posted number. The project page also asks through traffic to keep left so vehicles have room to merge.

ITD describes these five miles as the most heavily traveled and congested stretch of the corridor. The crossover is how crews rebuild the westbound bridges over Huetter Road, Atlas Road and Prairie Trail without closing the interstate. That's why the closures land where they do. Prairie Trail closes when the westbound bridge over it comes down, and Huetter Road closes once the existing interstate bridges above it are demolished.

Every detour points at Seltice

Look at ITD's alternate routes together and the pattern is clear. Eastbound drivers at SH-41 go to Seltice Way. Huetter Road drivers south of the interstate go to Seltice Way. The Centennial Trail is closed between Northwest Boulevard and Atlas Road for the widening and city waterline work, and ITD sends walkers and cyclists along Riverstone Drive and the south side of Seltice Way.

Meanwhile, Post Falls is partway through its own two-phase Seltice Way Rehabilitation and Pipeline Project, estimated at about $7.9 million. As of the Coeur d'Alene Press's Aug. 16 report, the north half of Seltice was closed between McGuire and Chase roads, with traffic moved to the south half at one lane in each direction. The city's project flyer also says Mullan Road is closed to through traffic at Seltice Way, with access to the park and businesses via Chase Road. Homes and businesses along the work zone stay reachable.

The work goes well beyond repaving. It includes new sewer and reclaimed-water lines, stormwater improvements, signal upgrades and better pedestrian facilities. Public Works Director John Beacham told the Press the road has "slowly been crumbling over the years," and described the trade-off this way:

"We know that it's a disruption and, sometimes, there's just no way around that. But we try to make it either as quick as a disruption as possible or as painless as possible, and those two things don't always align."

The Press reported that Phase 2 is expected to run through 2027, with more utility, roadway, pedestrian and signal work. The city hasn't posted a newer public update on exactly which Seltice segments are open in October. Before relying on Seltice for a time-sensitive trip, check current signs and the city's notices; the August lane setup may have changed. What is certain is that the city's Seltice timeline and ITD's year-long crossover overlap.

Why this is happening now

Most of this work runs in daylight, during the commute, and that has frustrated a lot of drivers. ITD spokesperson Heather McDaniel addressed it directly in the Press. She said night work isn't practical for every task, because some highway work needs daylight and some depends on temperatures that overnight hours don't offer. She also pointed to cost: "Night work significantly increases project costs, and Idaho law requires ITD to award projects to the lowest responsive bidder."

The speed of the project is part of the reason too. McDaniel said available federal and state funding allowed the I-90 widening and the interchange updates at Highway 41 and Pleasant View Road "to move them into construction earlier than previously expected." The money comes mainly from Idaho's Transportation Expansion and Congestion Mitigation program, which lets ITD build sooner than it otherwise could.

Here is the longer timeline. Construction started in August 2025, and the widening is scheduled to finish in 2029 with four lanes in each direction between SH-41 and US-95. If the crossover begins around Oct. 20 and lasts a full year, it ends around fall 2027, about two years before the full project wraps up. The Press put typical delays this summer at roughly 10 to 20 minutes for drivers passing through one or two work zones, and said some commutes take much longer.

Trip by trip through the first month

ITD's guidance changes depending on where you start, so here it is by trip:

  1. Heading east from SH-41 before Oct. 9. The eastbound on-ramp is closed. Take Seltice Way west to the on-ramp by the Seltice Way bridge.
  2. Crossing under I-90 at Huetter after the shift. Expect a closure of up to two weeks. North of the freeway, use Mullan Avenue or Poleline/Hanley Avenue. South of it, use Seltice Way.
  3. Coming home westbound late at night. The westbound SH-41 off-ramp is expected to close overnight for several weeks starting in late October. ITD says it will share specific dates as the work gets closer.
  4. Walking or riding. The Centennial Trail segment from Pleasantview Road toward Spokane Street is scheduled to reopen after Oct. 14. Its $280,051 resurfacing was paid for by Kootenai County, Post Falls, Coeur d'Alene, the North Idaho Centennial Trail Foundation and a state recreation grant. Prairie Trail under I-90 closes for about a week starting Oct. 12.

ITD suggests signing up for its email and text alerts and checking Idaho 511 before you leave, since dates in its releases can shift.

Plans close to home during the first weeks

Some of the season's local events are on Post Falls streets you may already use, which can make them easier to fit around the shift.

The Flying Pickle, the new 83,000-square-foot pickleball facility on Beck Road, has 24 courts, a restaurant and bar open to the public, and a Selkirk Pro Shop. Its first tournament was planned for Oct. 18, the Sunday of the tentative paving weekend. The city's Pumpkin Bowl men's flag-football tournament is Saturday, Oct. 24, at Warren Field, 105 N. Idaho Street. Post Falls City Hall hosts free, Under the Sea-themed trick-or-treating on Friday, Oct. 30, from 2:30 to 4:30 p.m. at 408 N. Spokane Street. The free Holiday Craft Fair follows on Saturday, Nov. 7, from 9 a.m. to 3 p.m. at Trailhead Event Center, 12361 W. Parkway Drive, and Black Bay Depot, 1211 E. 3rd Avenue.

The crossover is expected to stay in place through next fall, and Seltice Way's Phase 2 runs through 2027, so the drive between Post Falls and Coeur d'Alene will look like this for a while.

If the I-90 work has you rethinking your daily commute, or wondering how a year of detours could affect timing on a future move, Natalie Priebe is glad to talk it through. Contact Natalie for a personalized market consultation.

Discover the Difference

I am committed to guiding you every step of the way—whether you're buying a home, selling a property, or securing a mortgage. Whatever your needs, I've got you covered.

Follow Me on Instagram