By early October the concrete was going in at Ramsey Road and Honeysuckle Avenue. Crews were finishing the center and splitter islands, sidewalks were taking shape, and striping had started. The city's projects page, updated October 7, still listed the closures that have shaped west Hayden driving since June. Ramsey is closed to through traffic between Hayden Avenue and Prairie Avenue, and Honeysuckle is closed between Atlas Road and Reed Road.
The barricades will come down soon. The intersection plan that replaces them is built for the long term, though. The signal that went up at Hayden Avenue and Ramsey Road this month is expected to stay for roughly eight to 10 years. A second roundabout at Hayden and Atlas is being readied for bids, and the Honeysuckle Beach boat launch is on its own construction clock over the same off-season. Reopening Ramsey and Honeysuckle is one step in a longer sequence of west Hayden projects.
Why October 5 came and went
October 5 was the reopening date the city gave the public. As of the October 7 update, the closures were still in place. The Hayden Reporter has followed each change order to the LaRiviere Inc. contract, and its reporting shows the slippage came mostly from what was underground and from utility crews sharing the site.
| Milestone | Substantial completion date |
|---|---|
| Original Notice to Proceed | Aug. 28 |
| After Change Orders 1 to 3 | Sept. 2 |
| After Change Order 4, approved Sept. 22 | Sept. 24 |
| Proposed Change Order 5, on the Oct. 13 agenda | Oct. 6 |
Change Order 4 added $9,582.13 and 13 contract days. Most of the money paid for 493 extra cubic yards of excavation after the profile of Ramsey's north leg was revised. Some of the time covered a damaged Ziply line, Avista lowering a gas line, buried concrete-like material in the sewer force-main trench, and Hayden Area Regional Sewer Board air-release valves that did not work as expected while the force main was drained.
The proposed fifth change order continues the pattern. In its October 12 report, the Hayden Reporter describes contractor requests tied to Ziply Fiber, Spectrum and underground conflicts at the stormwater drywells. Welch Comer Engineers recommended four days for Ziply, one of the five requested for Spectrum, and one of three for the drywells. It also covers a September 14 directive from Public Works Director Alan Soderling to rework the pedestrian ramps, bicycle ramps, curbs, approaches and sidewalks on all four legs of the roundabout. That work added two days and $2,555.35.
Even so, the fifth change order would lower the contract price, to $1,743,027.20. Deductions for Hayden Lake Irrigation District hydrant and water costs, plus inspection fees for Saturday paving on September 26, outweigh the cost of the ramp revisions. The original May award was $1,714,895.55. Once Change Order 5 is counted, the project would carry 30 added contract days.
The Hayden Reporter also points out that the October 6 substantial-completion milestone "does not independently establish a public reopening date." Until the city posts an update, the actual reopening day is still open.
The signal at Hayden and Ramsey is built to stay a while
Drivers detouring north this summer passed through the four-way stop at Hayden Avenue and Ramsey Road, under a temporary signal the city put up to handle the extra traffic. On October 7 the city's contractors finished a spanwire signal there. The city says it "permanently replaces" the four-way stop. It includes detection meant to cut queuing and dead time, and it adds lighting on the southwest and northeast corners.
The same city page also lists a Hayden Avenue and Ramsey Road roundabout as an upcoming project. Its design is finalized, and right-of-way negotiations are the next step. In its August 28 report on Soderling's council update, the Hayden Reporter said the signal, a $142,925 contract with Thorco Inc., "is expected to remain for approximately eight to 10 years while the city secures the right of way and funding needed to construct the planned roundabout."
That puts the roundabout at Hayden and Ramsey out to around the mid-2030s. The signal is the intersection people will drive through for most of the next decade.
The order of operations is deliberate. City officials told the council that buying right-of-way first makes Hayden more competitive for state grants, because most outside programs won't pay for land. Funding from the Hayden Urban Renewal Agency can strengthen an application by adding a local share. Soderling said "anything you can do to be ahead of somebody else" helps when grants open up.
Atlas moves to the front of the line
If west Hayden gets a second roundabout before Ramsey's, it looks likely to be at Hayden Avenue and Atlas Road. That plan changed within a few weeks.
In late August, the Hayden Reporter reported a plan to widen Hayden and Atlas with three new left-turn lanes and then install another temporary signal, possibly over the winter. At that point the city had a designed roundabout but no money to build it. It had agreements on nearly all the needed properties, with one or two unresolved.
By October, the roundabout itself was moving. A $57,300 engineering amendment with Welch Comer & Associates, on the council's October 13 consent calendar, would revise the design and prepare bid documents. According to the Hayden Reporter, the amendment would:
- Remove the eastbound slip lane at the southwest corner, so drivers turning right onto Atlas would go through the roundabout
- Revisit whether a planned rectangular rapid-flashing beacon for pedestrians stays in the design
- Add gravity sewer through the intersection, including about 270 feet south along Atlas Road, to prepare the area for future development
The schedule in the amendment anticipates private utility relocation during fall and winter 2026-27 and bid advertising in late winter or early spring, with construction anticipated to start in spring 2027. No construction contract, construction cost or completion date has been set. Approving the amendment would not approve a construction contract.
Utility work came up throughout the Ramsey-Honeysuckle change orders. At Atlas, the city is scheduling it before construction starts.
Two more corridors are in the queue. Hayden Avenue and Huetter Road has a roundabout in final design, with right-of-way negotiations next. On Government Way, a study with the Hayden Urban Renewal Agency is finished. Design is complete for a signal at Miles Avenue, and a southbound right-turn lane at Honeysuckle Avenue is in design.
At the lake, the boat launch has its own off-season schedule
Honeysuckle Avenue ends at Honeysuckle Beach, where the city is preparing for a different kind of rebuild. Photos on the city's project page show spalling concrete, a worn ramp with poor drainage, and the south dock sitting on the ramp.
The council-approved funding plan totals $325,000. That's a $250,000 grant from the Idaho Department of Parks and Recreation's Waterways Improvement Fund plus a $75,000 city match. According to the city's grant application, the money covers:
- Regrading and resurfacing the asphalt and concrete launch ramp
- Moving the south dock about two feet south so it no longer rests on the ramp
- Building an ADA-accessible concrete walkway linking the north dock to the south end of the facility
In June, the city said it expected construction to begin in fall 2026. The grant application estimates work from September 1, 2026, to June 1, 2027, and the Hayden Reporter reported a grant period that runs through June 30, 2027. No source so far confirms that work has started, or says whether the launch or beach will close and for how long. The city's projects page is the place to watch before planning a late-season launch. The schedule points to work over the winter, with a ramp and walkway ready by next summer.
Where the holiday calendar meets these roads
Two city events at McIntire Family Park fall after the contract milestones. The first is the Veterans Day ceremony and 2026 Distinguished Veteran recognition at 11 a.m. on November 11, on the McIntire Family Park stage behind City Hall. Then on December 5, the Hayden Lights parade runs from Hayden Avenue south along Government Way to Honeysuckle Avenue, followed by the tree lighting at McIntire Family Park, 8930 N. Government Way. If Ramsey and Honeysuckle reopen as those milestones suggest, west-side traffic heading to both events will have the new roundabout open and the Hayden and Ramsey signal running.
Road projects like these change which routes make sense, how long a trip across town takes, and what the neighborhood looks like a few years out. If you're thinking about what the west Hayden intersection plans mean for your home or a move nearby, Natalie Priebe follows these projects from the council agenda to the finished pavement. Contact Natalie for a personalized market consultation.